A Carbon Takeback Obligation on UK Production: How Much CCS Could It Fund?

Published: November 23, 2026

Written by Stephanie Loo.

Could North Sea producers fund the UK’s carbon capture commitments?

The UK government has committed up to £21.7bn over 25 years to its first two carbon capture and storage (CCS) clusters, mostly recovered through energy bills. With further public funding now under pressure following the October 2026 Budget, this briefing assesses an alternative: a Carbon Takeback Obligation (CTBO) requiring UK oil and gas producers to permanently store a rising share of the CO₂ released when their products are burned.

Key Findings

  • Early storage. An obligation of 4% implemented in 2030 would fund around 4.3Mt a year of storage, roughly HyNet's initial capacity.

  • Track-1 capacity. At 16% reached in 2035, the obligation would fund around 10Mt a year, enough to cover both Track-1 CCS clusters, which is the capacity covered by the current £21.7bn government commitment.

  • Cost to producers. The estimated cost of a UK CTBO starts below £4 per barrel of oil equivalent, increasing to around £13 over the next five years as the obligation rises assuming the cost of CCS does not decline. For comparison, the starting annual cost of the obligation is about a third of the amount raised by the Energy Profits Levy in 2025-26.

  • Consumer prices. Because UK oil and gas is priced internationally, an obligation limited to domestic production is not expected to affect UK energy prices.

  • International context. The EU introduced a comparable obligation on producers in 2024. Early evidence points to increased storage project activity.

Read the full briefing

Policy Recommendations

  • Create the power in primary legislation. Government should use primary legislation to give the Secretary of State a power to introduce a storage obligation covering all UK oil and gas licence holders, using the next suitable energy bill. Setting the obligation rate and trajectory in regulations would allow them to be adjusted as costs change.

  • Certify stored CO2. A designated administrator should issue one certificate for each tonne of CO verified as permanently stored. Only independently verified, permanent storage should count towards compliance.

  • Maintain CCfDs for capture projects. Until certificate trading is established, government should continue to guarantee capture projects an agreed price per tonne captured to provide continued investor certainty and lower borrowing costs.

  • Sell Track-1 certificates at a fixed price. Because government is paying for Track-1 capture and storage through its contracts, it would hold the certificates for those tonnes. In the early years, government should sell these certificates to producers at a fixed price.

  • Use sales revenue to provide a funding route for Track-2 CCS clusters. Revenue from selling Track-1 certificates should be used to provide government support and market certainty for Track-2 clusters, Viking and Acorn.

  • Open the market to new storage. From 2034, the obligation would exceed initial Track-1 volumes and producers would need certificates from new storage. Government should set out early how other clusters such as Viking, Acorn, and Peak could sell certificates to producers, giving them a commercial revenue stream and reducing their reliance on public funds.

  • Review in 2035. Government should review the trajectory in 2035 in light of CCS costs, energy prices, and international policy developments, and decide whether to extend the obligation to imports.